Suppose, if R3 has multiple source list in R/3 for a single material and plant combination, does multiple T-lanes gets created automatically in APO while ciffing or does any extra enhancement is needed ?
Further, how is the Procurement Priority field in the Transportation lanes gets set in the case of multiple sources? Does all of them have Procurement Priority as 0?
Any ideas on this ?
Thanks
Yes it will create multiple TL in APO with all having priority 0.
We had the same issue.
To automaticall create in APO you just need to setup IM for inforecord/Contract/SA as per your requirement in R/3 by CFM1 and CFM3 .
Manish
Edited by: Manish Kumar Rathi on Oct 15, 2008 11:01 AM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Imp tcode to change it ;
/SAPAPO/PWBSRC1 - Procurement Relationships
Or use MASSD or LSMW or CATT or manually do it in TL.
if you dont want to do it manually , you need to implement it through user exit.
tcode:SMOD
below user exit will help you .
APOCF026 User-Specific Enhancement: Source of Supply
APOCF032 Inbound Processing: Sources of Supply
Hope it will help you .
Manish
User | Count |
---|---|
9 | |
4 | |
3 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.