on 10-15-2008 12:51 PM
Hi
When we going to close the production order following error came.
( Unprocessed future change recs for order 800097653 prevent del. flag/completion)
As mentioned in the procedure when we go to :
Reprocessing incorrect actual cost calculations ( COFC )
It gave another error as follow :
No price could be determined for internal activity 10-140 MPA020
But we have already updated the activity pprice and we are goin to close the 2006 production order, Pls advice how to solve this issue.
Thanx in advance.
Dear,
Use T Code KP26 and maintain the activity types/cost centre mentioning the fiscal period and version. I'm sure it will solve your problem. Or if possible take help from CO consultant.
Then go ahead with future change records from confirmation processes - COGI, COFC
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.