Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Two PSA requests loaded with one DTP Delta

Hi,

I have an Info Package Full Upload loading data into PSA than DTP delta loads data into Infocube.

The problem is DTP is taking two PSA request and loads it into Cube as one DTP request.

There are doubled quantities in infocube.

There are 4 PSA request and DTP takes the 1st one and 3rd. Loading is once day. PSA request are removed if older that 4 days.

What shoud be done so only the newest PSA request is taken into consideration.

Thanks for help

Mariusz

Former Member
Former Member replied

Bach,

Try setting the DTP to Delta and check the Option of Only Get Delta ONce - it will pick the oldest request in PSA which has not got updated in the data target.

Arun

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question