Confirmation of hours for Production orders

Dear all,

i have a scenario whereby one of the operations in the routing was not linked to any activity type and at the same time, a production order of the same material number was created copying both the bom and routing. It is only months later then the activity type was allocated to this work center. Thus if i doing confirmation for my work center at the current stage, will the actual hours and cost be posted to the system??

Thanks in advance

Regards

Yiming

Former Member
replied

Dear,

If any transication happend then Read PP master data will not work meas if good has been issue to order.

Best way you can reverse good isuue and active TECO to Production order CO02FunctionRestricte processing-- and active TECO.

The following actions are executed if an order is set to Technically complete.

The order is not relevant for MRP

Reservations are deleted

Capacity requirements are deleted

Purchase requisitions for external operations or non-stock materials are deleted

The order and its operations receive the system status Technically Completed.

If an order is technically complete, you cannot change it. The fields in the order are displayed but cannot be changed.

And create new order and excute it.

Regards,

R.Brahmankar