on 10-15-2008 8:50 AM
Hi gurus,
Can you please tell me what are the different steps in configuration of batch determination function. At what point of time we should perform this? Can we do it at planned order level? Please reply
Regards
Rajib Pathak
OK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajib,
Refer below Link for Help on Batch Determination,
[Batch Determination Configuration|http://www.sap-img.com/materials/config-setting-in-batch-management.htm]
[Batch Determination Help|http://help.sap.com/bestpractices/BBLibrary/Documentation/G91_BB_ConfigGuide_EN_DE.doc]
[BB Configue Guide for Batch Determination|http://help.sap.com/bp_bblibrary/600/documentation/H20_BB_ConfigGuide_EN_DE.doc]
You can perform Batch Determination at the time of,
- Goods Issue or Transfer (Inventory Level)
- In Process \ Production Order
- Batch Determination in Sales and Distribution.
But you can not do Batch Determination in Plan Order.
Regards,
Dhaval
Edited by: Dhaval Choksi on Oct 15, 2008 1:46 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Dhaval,
I am talking about production order only. starting from planned order generation to production order release, at what point of time i can do batch determination.After batch determination, system will create reservation for the components. If for one component we need multiple batch, then will it be visible in production order(all the batch no)? please help.
Hi Rajib,
If You want to do Batch Determination in Production Order than create Batch Determination Strategy by using T.code COB1.You can put Batch Split up to 999 Nos. Means System will split the required qty up to 999 Batches in case of Qty is not fulfilled by single Batch.
After Batch Determination In Order itself System will auto update the Order reservation also.You will selected Batch No. in Reservation also.
One more thing If you want to do Auto Batch Determination for components then tick Option 3 For Batch Entry in MRP 2 view of Material Master.
Regards,
Dhaval
User | Count |
---|---|
86 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.