on 10-15-2008 8:29 AM
Dear Gurus
If I want to know what is the actual lead time i.e (workcenter capacity situation+the timings mentioned in the material master workscheduling veiw) for a particular finished product can I decide from the sales order so that I can commit the reqd delivery date. There is a option in the sap library that tells planning table can be accessed through sales order but how that is not clear.
Waiting for your views
Sandip Sarkar
Sap pp consultant
Hi,
you can see the work center capacity situation for manufacturing an item in the salesorder. But it needs Assemble to Order strategy. Anyway u can see the material details in the sales order.
Kiran.