pipe line material - complete process

Hi,

Can anyone provide me the complete process for pipe line material..

ie. frm mmr to invoice setlement.

thanks in advance..

Former Member
Former Member replied

Hi,

For Pipeline Process,

1. Create Pipeline Material under material type PIPE

2. You need to maintain the Pipeline Info Record in ME11. Here maintain the Prices and Tax Code mandatory

Also in SPRO > Enterprise Structure > Assignment > Materials Management > Assign standard purchasing organization to plant

There will not be any PO and GR Process for Pipeline materials. We consider that materials are available via Pipes in our plant and we have tp directly book consumption and then settlement of the same.

If Stock is directly consumed from Pipeline Stock via 201 P or 261 P via transaction MB1A or MIGO then following FI Entry will appear;

(GBB-VBR) Consumption Account - Dr
(KON) Pipeline Liabilities - Cr

Now do Pipeline Settlement in MRKO. Here you can not change the Invoice Value. Here following FI Entry will appear;

Vendor Account - Cr
Pipeline Liabilities - Dr

Prerequisite for MRKO: -

- Maintain condition record for output type KONS in MRM1

Then take printout of the Settlement Document in MR91.

Also refer following link;

[Pipeline Handling 1|http://help.sap.com/saphelp_46c/helpdata/en/fd/45c3fe9d6411d189b60000e829fbbd/content.htm]

[Pipeline Handling 2|http://help.sap.com/saphelp_erp2005/helpdata/en/4d/2b926443ad11d189410000e829fbbd/frameset.htm]