Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

Planning permitted in planning elements only Message no. BP024

Hi All,

I got this error message in CJR2 (wbs and Cost element) - detail planning. I already set the WBS with object indicator planning elements.

What should i do?

Cheers,

Nies

-


Planning permitted in planning elements only

Message no. BP024

Diagnosis

In the Project System configuration menu, the system manager or another authorized person can use the plan profile to determine whether cost planning is possible in all WBS elements or only on those designated as planning elements.

The plan profile for your project stipulates that cost planning is only possible in planning elements.

System Response

Processing stopped.

Procedure

You have two possible courses of action:

You must define planning elements for your project.

a) To do this, choose Project management -> Master data -> Work breakdown struc -> Change.

b) Enter a project definition and press ENTER.

c) Choose Goto -> WBS element overview -> Operative indicators.

d) Define your planning elements

Ask your system manager or some other person authorized to maintain the configuration menu.

Action by system manager

In the plan profile, stipulate that cost planning is permitted in all WBS elements.

Proceed

Former Member
Former Member replied

Hi,

Create a Status Profile ( T Code OK02) and assign it to WBS PHRE3PLH0810-PP-KT03 .

The one of status number in that profile should allow the Business Transaction '' 'write plan line items''. You have to set that status number to that WBS.

Regards,

Amit

0 View this answer in context