What is the meaning of Rem.Order Plan in the PS cost report S_ALR_87013558

Hi,

Does anyone know the meaning of "Rem. Order Plan" column in the PS Budget-related cost report-- S_ALR_87013558 Budget\actual\Commitment\Rem.Plan\Assigned? I understand all the other columns like budget, actuals, commitment and assigned, but I have no idea what the "Rem order plan' means?

Thanks,

Former Member
Former Member replied

In this report it is "Planned Cost - (Actual + Commitment)"

Venkat

Edited by: VenkatSrinvas Konda on Oct 16, 2008 8:09 AM