Standard Inport Package is getting failed at Convert Data Task

Former Member
0 Kudos

Hi All,

When running standard import package on any application, it's getting failed at Convert Data Task.

Do any body faced similar kind of issue, please let me know what might be the cause or any solution to the above issue would be appreciated.

Regards,

Sreekanth.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

The format of dimension members in the external file is different from the BPC internal format. Check your conversion file. The problem is with your conversion file.

For example:

In the external file Time dimension values is given as Jan, Feb, Mar etc..

In BPC asume you are maintaining time dimension members as 2008.Jan, 2008.Feb etc.

Then you should define this in conversion file. Jan should be replaced by 2008.Jan when it enter BPC application. Also, the values you define in the Internal format should be maintained as master data (dimension members).

regards,

Lokesh Nandula

Former Member
0 Kudos

Hi Lokesh,

I am trying to check my conversion files. So far conversion files look good.

Are you able to run standard Import Package with Convert Task.

Regards,

Sreekanth