on 10-14-2008 1:59 PM
When I am creating PO w.ref to to existing Valid contract,system ask me to enter price.It is not picking up gross price from Contract.What could be the problem?
Hi venkat,
Please goto conditions tab of PO, press "analysis" button. It will give to details of all price determination attempts. under gross price condition, some access sequence will give you result of determination of price from contract too. In my system, it is sequence no 12.
Please check here in details that what access is not getting met for correct determination.
Sanjeev
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Plz check the Pricing Conditions validity in the contract for the respective items.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
100 | |
11 | |
11 | |
6 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.