delivery completed indicator in PO

Former Member
0 Kudos

Hi,

What is the use of delivery completed indicator in delivery tab in PO.

Tx

Uts

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi

It means that there is no open material available for the corresponding item.

Thanks

Prashanth

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

When you set this indicator the PO is not considered for planning and will not appear in MD04 t code.

This is purely for MRP but you can still receive goods.

regards

suresh

Former Member
0 Kudos

HI,

It is used to short close the PO whose deliveries are nor expected to come there after.

You can make GR for the balance quantity in future also.

Rgds

Srini

former_member581212
Active Contributor
0 Kudos

hi,

This indicator is used when you don't expect any further deleiveries for the material...

But its possible....after ticking on it...if there is more GR for the PO...then the open PO qty doesnot change....

Also this indicator is must if you want to archive your doc...

Hope it helps..