on 10-14-2008 12:25 PM
Dear all
When i create the PO for Project material (a/c assignement is 'P'), I get this error,
"Account 400000 requires an assignment to a CO object"
Kindly suggest me.
Thanks
Please check if the G/L account 400000 is assigned to the same chart of accounts under the controlling area. check in T. code FSP0 for the proper maintenance of G/L account.
Hope this helps.
Venu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As u r creating a PO with account assignment "P", u should maintain WBS element on which u would like to capture the PO Cost in item details, account assignment tab.
Venkat
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Enter WBS element or Network in item details account assignment tab in PO.
Regards,
Chandra
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
As per the field status group of the GL (P/L) account , a CO object is made as required entry, which I think is correct.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please ensure to create your GL account as Balance sheet account and there wouldn't be any cost element created for this account.
Regards,
Amit
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.