cancel
Showing results for 
Search instead for 
Did you mean: 

CO error

Former Member
0 Kudos

Dear all

When i create the PO for Project material (a/c assignement is 'P'), I get this error,

"Account 400000 requires an assignment to a CO object"

Kindly suggest me.

Thanks

Accepted Solutions (0)

Answers (5)

Answers (5)

Former Member
0 Kudos

Please check if the G/L account 400000 is assigned to the same chart of accounts under the controlling area. check in T. code FSP0 for the proper maintenance of G/L account.

Hope this helps.

Venu

Former Member
0 Kudos

As u r creating a PO with account assignment "P", u should maintain WBS element on which u would like to capture the PO Cost in item details, account assignment tab.

Venkat

Former Member
0 Kudos

Hi,

Enter WBS element or Network in item details account assignment tab in PO.

Regards,

Chandra

Former Member
0 Kudos

As per the field status group of the GL (P/L) account , a CO object is made as required entry, which I think is correct.

Regards

Sreenivas

Former Member
0 Kudos

Hi,

Please ensure to create your GL account as Balance sheet account and there wouldn't be any cost element created for this account.

Regards,

Amit