on 10-14-2008 12:18 PM
Hi all,
Need to change material type of one material from raw material to semi finished goods how to do it?
rgds
srini
Hi
Use MMAM transaction code.
Thanks
Prashanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Use trasax MMAM
There give Material XXXXXXXX
New material type XXXXXX
And execute (F8)
Then save
Regards
Sujoy
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Use the T.code MMAM to change the Material type.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
USE MMAM tcode...
But before changing remind that you don't have any open document for the material remaining..for eg: PO, GR etc...
Hope it helps..
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.