on 10-14-2008 12:10 PM
Hi,
Could you please advice me, what the function of responsible and requesting cost center in WBS?
Is it possible to use only responsible cost center in a WBS without requesting cost center. I have a project structure where location and activities using only WBS.
Plz advice.
Cheers,
Nies
Hi,
Requesting cost centre is the cost centre which requests for certain activities to be performed by another cost centre which has the necessary resources (Responsible cost centre).
Requesting cost centre is not necessary, if the business scenario does not demand it.
Murali