how to configure a new factory calender.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear,

Factory calendar contain company specific dates such as alternate working Saturdays, Plant shutdown etc.

You can create your company factory calendar via transaction code 'SCAL'.

Assignment of the factory calendar by plant is done in transaction code 'SM30 - V_T001W'.

Please visit: http://help.sap.com/saphelp_nw04s/helpdata/en/f0/e702041d3fdd448629b4ee7c00de09/content.htm

Regards,

Syed Hussain.

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi

Regards

Ram

former_member581212
Active Contributor
0 Kudos

hi,

SCAL is the tcode to maintain the calender...

Assign it to plant in OX10....

Hope it helps..

Regards

Priyanka.P

Former Member
0 Kudos

Hi

Maintain the factory Calendar in transaction SCAL

SPRO-> IMG->

Assign the Factory calendar to the Plants in

SPRO-> IMG-> Enterprose structure-> Define-> Logistics general -> Define Plant.

You cannot assign factory Calendars to the Locations.

So you can maintain only one factory calendar to the locations