Production oderwise Total Labour Hour

Dear All,

I need a report which can give me Production oderwise Total Labour Hour.

Pls throw some light on that and let me know

Thanks.

Rgds,

Chetan

replied

Hi,

Check with the following :

In COOIS, by selecting "Operations" in List, give production order number and plant then execute, then goto change the layout as per your requirement (sum of all operation labour time's)

Regards,

Sankaran

0 View this answer in context