Dear All,

I need a report which can give me Production oderwise Total Labour Hour.

Pls throw some light on that and let me know

Thanks.

Rgds,

Chetan

Accepted Solutions (1)

Accepted Solutions (1)

muthusamy_sankaran
Active Contributor
0 Kudos

Hi,

Check with the following :

In COOIS, by selecting "Operations" in List, give production order number and plant then execute, then goto change the layout as per your requirement (sum of all operation labour time's)

Regards,

Sankaran

Answers (3)

Answers (3)

Former Member
0 Kudos

In COOIS, select List --> Operations

Enter plant and SYS Status--> CNF

Selection date

execute

Change layout as per requirements

former_member196398
Active Contributor
0 Kudos

Chetan,

Execute transaction COOIS transaction with List " Confirmations" and Profile "Standard", provide other selection criteria for orders like, Plant, Material, etc...

Regards,

Prasobh

Former Member
0 Kudos

HI

Just check in report CO28 in Operation and suboperation option. give order number and then select the activity i.e Machine or labour.

Please comeback if required.

Regards,

Anand.

Former Member
0 Kudos

Hi Anand,

Thanks for ur reply.

But I am not finding there Machine and Labor option.