I need a report which can give me Production oderwise Total Labour Hour.
Pls throw some light on that and let me know
Thanks.
Rgds,
Chetan
Hi,
Check with the following :
In COOIS, by selecting "Operations" in List, give production order number and plant then execute, then goto change the layout as per your requirement (sum of all operation labour time's)
Regards,
Sankaran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
In COOIS, select List --> Operations
Enter plant and SYS Status--> CNF
Selection date
execute
Change layout as per requirements
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Chetan,
Execute transaction COOIS transaction with List " Confirmations" and Profile "Standard", provide other selection criteria for orders like, Plant, Material, etc...
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
Just check in report CO28 in Operation and suboperation option. give order number and then select the activity i.e Machine or labour.
Please comeback if required.
Regards,
Anand.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.