Hello Friends,
Followings are the client requirements, Please give me your ideas :-
1 . Costing variant is same for all three - costing run, process order (plan and actual), means there is no prices variance on process order level. ( material at std price, Activity plan price, overhead fix%)
2. Alongwith this above client also need to capture actual result (material at MAP, activity at monthly actual price, overhead fix %)
In this case there is price and usage variance can see.
Now as I think that both scenarios are not possible on process order level. According to me we can do by a customize actual costing cockpit.
Need your openion that do we have any option thru standard funcations of sap to get this requirement. If you need any other explanation , please do let me know.
Thanks
Ravi
Thanks friends. I have done.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
10 | |
9 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.