cancel
Showing results for 
Search instead for 
Did you mean: 

Change Pur Org in SA

Former Member
0 Kudos

I want to change the purchasing Organisation in Scheduling agreement.Is it possible? How?

Thnaks & regards

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

HI,

Go to me32l and check the same.

Regards,

Prasanna

Former Member
0 Kudos

Not possible through me32l. Grayed out field.

Former Member
0 Kudos

Go to Spro>MM>Pur> Define doc type for SA..

here check the field selection Group for your doc type

and at Spro>MM>Pur>SA>field selection for doc layout

check the field selection for Pur Org for Trxn ME32L

Former Member
0 Kudos

for my doc type, the pur org field in selection group reference data,item is not appearing..pl. help.

former_member192897
Active Contributor
0 Kudos

Go to Spro>MM>Pur>SA>field selection for doc layout

check the field selection for Pur Org for Field Selection Key AKTV in Reference Data, Item tab Change the Pur Orgn to Optional and Save.

Former Member
0 Kudos

Thanks.For AKTV I have already put it optional, still it is grayed out.My field selection key is LPL & in that Purchase Organisation field is not there.

Former Member
0 Kudos

Check field selection for all the available groups..

Former Member
0 Kudos

I have checked all field selection keys & put optional wherever purchasing organisation has appeared. Stll,I am getting grayed out field.

Former Member
0 Kudos

If it is IDES, Pls create a new SA and check...

Former Member
0 Kudos

No.Its on Dev server.(same on PRD server.)

Former Member
0 Kudos

have you created SA directly or w.r.t PR/RFQ...???

Former Member
0 Kudos

Directly.

Is it like SAP has not allowed changing of Pur ORG once created, because it is a agreement between Vendor & Pur Org?

Former Member
0 Kudos

Check whether it is allowing to change the Pur Org for PO...

Former Member
0 Kudos

Yes It is allowing.In fact I have used it.

Actually,I have changed the pricing procedure & want that OLD Scheduling agreement pricing should be reworked based on this changed new pricing. For this, I need to change Pur Org once & restrore back to original.( Since I cannot change vendor) This worked well for PO.

Any suggestion?