on 10-14-2008 8:42 AM
Hi Gurus
i am getting error " The date 00.00.0000 is not convertible ( please correct) " . Please help me out of this problem.
Regards
Kaisar
Hi,
For the Material, in MD04, Check the planned Orders, production orders or Schedule line/Agreements.
Some where the Dates mentioned are of 00:00:0000.
If you correct that one, it will be through.
There is no smart work here, only hard work..
You need to go into all the line items of MD04 individually..
Regards,
Siva
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Kaisar,
Can you please explain where you are getting this error? Is it a Custom report you are executing? There may be a case when custom program was built they might not have considered the user Data format for conversion.. please check.
Regards,
Prasobh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear,
Please check are you maintaining any planning calendar in MRP2 view and you need to extend the calendar.
The extension depends on the dates on which requirments are created.
After MRP if the requirements dates then you need to extend the planning calendar after that.
Check whther you have maintain the 'Factory calendor' for your plant or not?
If you do this definitely you will not get error and if not then Extend the factory calendar validity.
Or refer the notes note 457994
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Brahmankar,
Thanks a lot for OSS notes. i have checked , the problem is very similar to the one i am facing, but its still unsolved. The factory calendar is defined up to 2015 and Total replenishment lead time is 0. Even then i am getting this problem.
Please help me out of this
Regards
Kaisar
Dear,
Please check calender assigment to the plant and try with extending validity period also. I think it will solve your problem.The total replenishment lead time in the MRP view in the material master is more than factory calender. Change TPL to small number or extend the factory calender.
Regards,
R.Brahmankar
Edited by: R Brahmankar on Oct 16, 2008 12:53 PM
User | Count |
---|---|
92 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.