on 10-14-2008 7:55 AM
Hi All.
I run MB51 (report RM07DOCS) with a predifined variant and get a list of material documents. Then GOTO> Detail list.
Is there a possibility to schedule RM07DOCS with a variant as a background job that would give detail list right away with a predifined layout.
thanks
Ivan Sobol
Edited by: Ivan Sobol on Oct 14, 2008 8:55 AM
Dear,
You need to execute MB51 with your selection fields, put the output list in ALV and then save a variante for this report. You go out the transaction and later you execute MB51 in background with this variant. If we define a background job for program RM07DOCS with a variant, the program uses the "hierarchy display only".
I hope that this information help you
Regards,
R.Brahmankar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Brahmankar
thanks for your answer. The variant for program RM07DOCS already exist and it works fine. I get the output but then i need to go to 'Detail list' where i need to choose specific layout. Layout is not for a variant of RM07DOCS but for a 'Detail list'.
And our user want to get 'Detail list' as final result of the batch job
May be there is any any report that could give sum (by quantity & Loc. curr. amount) for a specific movement type/period of time.
thanks
Ivan Sobol
Ivan,
When you run transaction MB51, change the layout as required and save it. Assign the saved Layout name to the Layout field in the selection screen of variant for program "RM07DOCS", now you can execute this program in background and you should get the output as defined in the layout.
Regards,
Prasobh
User | Count |
---|---|