on 10-14-2008 7:29 AM
Hi all,
My client is doing In process Inspection during Production process.
They are inspecting based on the Inspection Points (Shift wise).
If I add Inspection point referrence at Header level in routing, after adding the MICs in the required operation, while saving it gives an error message stating that "Maintain Inspection Point referrence at Operation level".
Task List contains error. You want to save or cancel.
How can I achieve this with out error.
Thnx in advance
Sam
Hi Sam,
Go to Routing and select the operation, and double click the operation. Then system will popup the new screen here under Quality management Inspection point tab choose No relation. and save the routing.
Check and give the feed back.
Regards,
S.Babusingh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Sam,
In the routing operation overview screen u have to assign any one of the following.
*time related,qty related,no relation.
you have to assign the frequency of RR.
Regards,
Selva.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.