PO Delivery date copy to MIGO

Former Member
0 Kudos

Dear All,

My requirement is PO delivery date should copy to MIGO delivery date(Item Level).

Please tell me steps.or Any Standard user exit or BADI is there,please provide me details.

Thanks & regards

Pavan

Accepted Solutions (1)

Accepted Solutions (1)

kunal_ingale
Active Contributor
0 Kudos

hi

u can assume ur posting date in gr as ur delivery date in po

so take help of ur ABAPer to link them

regards

kunal

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

There is no delivery date field in MSEG (material document item), so first you will have to find a not-used field to hold this data or to create a new field. Then ask an ABAPer to find the right user exit to populate the field. What user exit to use depends on what field is to hold the data.

Phyllis.

former_member581212
Active Contributor
0 Kudos

hi,

I think you need to take the help of ABAP consultant...ask him to provide the field and link for the del. date in the MIGO....for this you can refer the table EKET(Del. schedules in PO)...

Hope it helps..

Regards

Priyanka.P