Firm planned order

Hi PP Guru,

Please explain me what is Firm planned order

replied

Dear,

Firmed planned order means no automatic changes take place in order while running the MRP. It can be done with planning time fance.

For MRP type P1 & P2 system will firm the existing planned order.

If the planned order manually changed, firming indicator will appear in MD04 screen.

Firm Indicator (*) you can see in MD04.

Firm planned orders are not changed in the planning run. This means the system does not make any automatic changes to either the planned order quantities or dates. Firm planned orders can only be changed manually.

Regards,

R.Brahmankar