In KEPM transaction code,I have planned for version 1.Now i wanted to copy the data from version 1 to version 2.what proceedure should i follow for this.kindly help me
Thanks
Kishore
create a new planning package with characteristic Version = 2
(if you have defined verison 1 also on the planning level, you should create a new planning level)
then create a planning method under Copy with version 0 as source...
cheers
matej