Our sales plan in MC95 is in monthly buckets but once we transfer that to demand management via MC8G, the PIR in MD63 is shown in daily buckets. But we want to keep that in monthly buckets, what configuration should I check?

Regards

Corey

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hello,

Go to md62 and select the parameters push buton and enter the required data and save it, it will be your default setings for that screen

Answers (3)

Answers (3)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Go to MD63 or MD62 and press F5 user parameter select Period indicator M- month,

Or inside MD62 in scheduling tap also you can seclect it as Month.

Please try and come back.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi,

In initial screen of MD62 you have an indicator planning period (Under plannign horizon). Here you can select your period as month/week/day to display your requirement in desired time bucket.

Check this. Hope this is clear.

Cheers,

Himanshu

Edited by: Himanshu Saxena on Oct 24, 2008 1:25 PM

Former Member
0 Kudos

Hi,

In MD62 itself you can convert the daily bucket requirements in to the monthly buckets. It is very well possible.

regards,