I can`t dispatch a planned orden in CM21,CM25,etc

Hi Experts,

I have created a planned order and i can see it in CM21 o CM25. But when i want to dispatch it, nothing happened !!!

The planned order is not dispatched and the "planning log" doesn`t show anything.

Instead of, then production orders can be dispatched well.

Can anybody help me?

replied

Dear,

You can check the details in CM25.

Where you can see the dispatched order in the top.

The orders which need to be dispatched in the bottom.

In case of planned order you can see if the capacity requirements check box is checked if the order is dispatched.

overall profile SAPCRPG003 in CM25?

Activate for Finite scheduling check Box at workcenter.(CA02)

Select the Stategy profile as SAP___T001 inside the planning table (CM25.

In OPPQ (Overall Plant Maintenance) there is a setting for Conversions under the planned order section. If you click there make sure that you have a default order type assigned to the Planned order --> Production order option.

Regards,

R.Brahmankar