Hi,
We have changed the transportation lead time from 35 days to 30 days in material master. Please advice me what are the impacts on the existing datau2019s in the system and how the system is going to behave after this change.
Please advice meu2026
Thanks,
Rohith
hi,
The transportation lead-time is the time in days that is needed to organize the shipping of the goods. This might include booking a ship and reserving a truck from a forwarding agent. It is defined for a route.
The transportation scheduling deadline is the date on which you must start to organize the transportation of the goods. This deadline must be selected early enough to ensure that the means of transport is available by the loading deadline.
Hope its clear now...
Regards
Priyanka.P
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
While calculating the requirements ,decreased lead time (30 days) will be considered for order quantity& safety stock calculation.Hence you have reduced your lead time,proportionally the order qty & safety stock qty will be reduced.
Regards,
Ravindran
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
It wont have effect on the existing Open PO's & delivery dates in the PO.
During MRP run the requirements & safety stock qty will be reduced in proportion to the reduced lead time.
Please find the details of sample calulation.
days 1months inventory Ratio for 1 month
New Lead Time 35 30 1
Old Lead Time 30 30 1.166666667
safety stock= 5 New Min stock= 11.66666667(will be rounded based on rounding qty)
Min stock= 10 New safety stock=5.833333333 (will be rounded based on rounding qty)
Hope you will get some idea .
Hi,
Planned delivery time: Lead time which was discussed earlier with sample calculation.
Planned Delivery date: Delivery date will be triggered automatically in PO, based on the Planned delivery time which we discussed.
Please find the detail of a sample calculation, how the planned delivery date will behave.
Lets assume the delivery time & the scenario in PO
Planned delivery time 110 15-Oct-08 - Today date ( PO creation date)
2-Feb-09 - Delivery date triggered in PO
Planned delivery time 115 15-Oct-08 - Today date ( PO creation date)
7-Feb-09 - Delivery date triggered in PO
Regards,
Ravindran
Hi,
According to your example, if we created a PO on 15-Oct-2008 with the effect of old planned delivery time (115 days) the delivery date should appear as 7-Feb-2009. And today (16-Oct-08) we are changing the planned delivery time to 110 days. In that case how the delivery date is going to be in the old PO which was created yesterday? Will it be 2-Feb-2009 or 7-feb-2009??
Please advice meu2026
Thanks & regards,
Anujan
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.