SOP demand and splitting issue

Former Member
0 Kudos

Good afternoon,

I am loading independent requirements into SOP (via MC88)

I have set the following:

Defining period split for automatic split: OMPH

Assigning period split of MRP group: OMPS

Consmption mode: OMPG

The required results are:

The forecast is split from a monthly Qty to a weekly one

The Independent requirements for the short term plan are ignored

I have tested these in our Dev and Quality enviroments but it is not working in our Prod enviroment, can anyone point me in the direction or what to check?

Thanks in advance.

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Issue with transport into PR client