on 02-08-2006 6:49 PM - last edited on 02-04-2024 1:57 AM by postmig_api_4
hi
When I try to create a project cycle in solution manager by selecting my solution manager project and clicking on "create project cycle", it logs on to the DEV system and then it gives me an error saying "Internal phase controller problem".
I got this SAP note number 892142 which i applied, but still don't know what is to be done after this??
Any suggestion are welcome
Thanks
Abhi
I have the same problem...but I don't understand why It should depend on something about cproject...To create task list is it a mandatory activity to create cproject?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey abhi,
How about rewarding points if my post helped you solve the problem ??
If my post didnt solve the problem, then how did you solve it, plz do mention..
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hey Abhi,
Go to Satellite system and execute tcode spro,
Go to spro of solman, sap solution manager-> scenario specific setting-
> change request mangement -> extended configration->change transaction-> cprojects-> check prerequsite for phase shift,
You will have to create project type and phase shift in satellite systems...
Regards,
Anand.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
101 | |
13 | |
13 | |
11 | |
11 | |
7 | |
6 | |
5 | |
4 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.