on 10-13-2008 4:31 PM
Hi gurus,
Plz tell me the difference between strategy 50 and 52.
Thanks,
Sachin
Thanks.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
The difference between strategies 50 and 52 is in how the sales order itself is planned. In strategy 50, the sales order is planned in a separate make-to-order segment - in this case, stock at the plant is not considered during the planning. In strategy 52, however, the sales order is planned in the net requirements (plant)
segment - in this case, stock at the plant is considered in the planning.
For further information, please refer to the following chapters of the SAP R/3 documentation:
Logistics (http://help.sap.com/saphelp_erp60_sp/helpdata/en/cb/7f9b7043b711d189410000e829fbbd/frameset.htm)
>Strategies for Make-to-Stock Production
>Planning w/o Final Assembly and w/o MTO (52)
>Strategies for Make-to-Order (MTO) Production
>Planning w/o Final Assembly (50)
This information should help, if not please let me know.
Bye,
Gabriel Souza
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.