Hi Experts,
My requirement is to block PP work centre when maintenance schedule the equipment for preventive maintenance. I am making system condition as zero in generated preventive maintenance order but basic finish date is not changing in the order automatically. Can anybody please explain how to bring this? Finally my requirement is system should change basic finish date and time as time given in operation of task list.
Thanks in advance.
best regards,
Srinivas M
Thanks..Kushal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Srinivas,
Check T code OPU7 and chesk the setting for Adjus dates. And Scheduling type.
Praveen.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check in the Adjust Dates : Adjust basic dates, adjust dep. reqmnts to operation date.
sheduling type as Only Capacity Requirement.
then your transaction, this will adjust basic start date w.r.t capacity availablity, prior to this you need to maintain the resource in the Equipment master data Location tab work center mention the resource number.
then try your transactions.
Regards,
Praveen.
Hi Praveen,
I have done all setting and tested but there is no change.
My client requirement is like this - whenever maintenance plans are scheduled, for the scheduled dates, production capacity should not be considered by production. We could do this for breakdown orders but not happening for PM orders unless we change the finish date.
The issue is to get the finish date automatically when scheduling maint.plans with respect to values given in operations. Please suggest how to get the basic finish dates automatically.
best regards,
-Srinivas
Dear,
Can you tel me how much exact total hours for the operation? See if your total hours of Job is 24 and three person employed then job will finish in one day if capacity of three person is 100 %.
Like this take your job hour more so that date can be shifted while selecting sheduling type. What I explained above you will not see any change in date. Just take the working hour more and do forward scheduling. Your start date will remain same anf finish date will change.
Regards,
Kaushal Rai
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.