MRP create 1 PO with several line items

Former Member
0 Kudos

Hi,

I have the following requirement.

Material A demand is 5 PC

Material B demand is 3 PC

and both are procured from same vendor

After MRP run 2 seperate POs are created.Now my client wants only 1 PO to be created instead of two and that one PO should have 2 line items for each Material A and Material B.Please note that the header material for A and B are different and hence I can not define the BOM to take care of this requirement.

Please suggest. Rewards

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

It is not possible to convert the no of PR into a single line item of PO.

Please refer this link ,

[one PR|http://www.sap-img.com/pp006.htm]

Regards,

R.Brahmankar

Answers (1)

Answers (1)

Former Member
0 Kudos

Ranojoy,

After MRP run system would create 2 different purchase reqn's for the 2 materials. You can go to ME21n, drag these 2 requisitions into the same PO & that would result in a single PO with 2 lines.

Alternatively you can do the same with ME58 & ME59, which are mass processing program, however please carry out a test run before proceeding to use mass transactions.

Rgrds,

Vivek