Hello all,

i am going to create std cost estimate for finish material with ck11n the following errors comes

No structure could be determine for internal activity (power), messege no. ck694.

but i have defined all activity price /costcenter/ bom routing , kindly help me out as no std cost estimate has been carried out through ck24

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member184655
Active Contributor
0 Kudos

Dear Premkumar,

Check whether have you maintained a proper per hour rate for the activity type Power & a Cost center

combination in T Code KP26.Once if this is correct check whether have you maintained the correct cost

center in the work center.Also the validity dates should be matching with each other.

Also check in the material master of the product for which you are doing the cost calculation in costing 1

view whether the check box for with quantity structure is included.

Which means it takes a BOM + Routing combination.

Regards

Mangalraj.S

Former Member
0 Kudos

Hi,

Check your activity type(Power) KL03 and check planning in KP26 for particular activity type(power) and Cost center combination for current fiscal year.

Thanks,

Rau

Former Member
0 Kudos

Hi

Have you tried to double click on the message, it may give you more info with regrad to the error.

Reagrds