Generation of Requirements Automatically
Dear Experts,
Is it possible to generate requirements for externally procured materials automatically without running MRP ?
Suppose if the Re-order point for a material is maintained as 100 and if the stock level goes below 100 the system should generate the requirement.
Please propose whether any function available in comsumption based planning to meet the above requirement .
Regards,
Ram
Former Member replied
Hi,
This might be an alternative soluton (KANBAN w/o MRP):
http://help.sap.com/saphelp_47x200/helpdata/en/cb/7f8afc43b711d189410000e829fbbd/frameset.htm
(requirement wouldn't be triggered automatically, and your whole supply chain process should be suitable for this sceanrio...I mean it is not just 'Customizing'...
Anyway, I don't think you would have chance to get auto PurReq w/o MRP run in standard SAP)
Regrads,
Csaba