stock to be consider while MRP

dear PP Gurus,

i have created plant as subcontractor(vendor) and transfer material from plant to vendor stock.

Now i am running MRP, while running MRP it is not considering the stock available at vendor, i want system to consider the stock available at vendor.

please guide

thanks in advance

Kailash N. Thakkar