hi sapgurus,

i have an issue,

i create a P.O. with quanitty of 100 kg, then i did GR only 50 kg and then i though i am no more interest in this vendor and then i flag

the Delivery Completed indicator in P.O. and when i go for GR once again, the system is still allowing to accept the goods wrt to that P.O. whicch supposed to be not. that is it should not allowed to post but system is allowing and plzzz can u tell me the some kind of testing where i can block such type of material for procurement purpose

thhanking you.

Delivery Completed" Indicator in Purchase Order Item"

Former Member
replied

hi,

In the std sap system, you are allowed to post the GR again even you have ticked for the del .comp indicator...

But when you post the GR after this, the open PO qty will not change...pls check...

Hope it helps...