Hello all,

How can i delete future std. cost estimate through ckr1 , kindly suggest me the process to be done.

Can i mark and released the std cost estimate of a material which has already costed inthe same month.

Suggest soon

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi

You delete a future standard cost estimate via CKR1 by:

Entering the Company Code

Plant

Material Number

and then in Control Parameters select: Future Satndard Cost Estimate

Deselect: Test Run

Click the Execute button

This will delete the future cost estimate (you do not have to click the save button).

This will delete the future standard cost estimate.

The answer to your second question is "No". A material can not have two marked and released cost estimates in one month. The material master only has one standard price and this can only reference one standard cost estimate. If for what ever reason you need to re-cost a material in a month you must first delete the standard cost estimate.

Regards

Rob Viljoen

former_member740051
Contributor
0 Kudos

Hi,

Go to CKR1 and enter the company code, Plant and material no. Select the button Future Std cost estimates" and uncheck test run and execute.

It will detele the marked cost estimates

Hope, it helps!