Hi,experts,

In my project, my client dont want to collect factory overhead(labor,machine,etc) by production order confirmation, and he want to collect the factory overhead through Percentage. For example , the material overhead of a production oder is 5,000 $ and the rate is 5%, so the factory overhead is 5,000 * 5% = 250 $ . How to realize this? Could you give me some advise?

Regards

Joey