I've a question regarding the re-synchronisation between cProjects and PS:

What will happen if I am using the hierarchical accounting with PS when I used the automatic accouting and change something in PS.

How is the synchronisation working?

Thx, Vanessa

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hello,

This is specified in Project Type customization, Type Of Transfer.

For eg: If you have specified as 'As of Status "Flag for transfer"-Automatic', first time it will create PS structure when you change the status as 'Flag For transfer' and Save.

Thereafter, for every change when you save, the changes get replicated to PS.

Regards,

Remya.