PROBLEM IN mrp

Former Member
0 Kudos

Dear cons

we have one material type i.e- FERT(finished). under this material type we have 10 no. of material. we want to create only one P.R by taking this 10 no. of material. that means we will create a P.R & this P.R contains 10 no. of line items. how it is possible when we run MRP for creation of P.R . pl. give me some idea regarding configuration setting as well as some t- code so that we can run MRP for multiple material under one P.R NO.We are able to create for single material but not for multiple material. pl. helpme.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

FERT by definition is a finished material. Meaning one which can only be sold. That is you cannot procure, u cannot perform activities on this material etc. Hence the MRP is running correctly. In case u want the material to be procure able as well as u want no activities to be performed than u can create it as trading goods. In case u want to perform some activities also then create it as semi finished goods.

Former Member
0 Kudos

O.K. PL. TREAT IT AS A SEMIFINISHED PRODUCT.

Edited by: nirupama swain on Jan 20, 2009 11:27 AM

Answers (0)