Need help as follows-

A project structure is created and released. When additional WBS is added,the status of the same is 'REL' automatically. But when activity is assigned to the Released WBS , the status is 'CRTD'.

The requirement is that when activity is assigned to a Released WBS, the status of the same should also be 'Released'.

Former Member
Former Member replied

Hi,

go to OPSC and tick the release immediately indicator.

Regards

Vivek Tripathi