Project Stock

Former Member
0 Kudos

Hi guys

I would like to procure item with account assignement for project WBS elements.

What are the settings that I need to do in the material master record and the WBS?

I have never work with project stock, does anybody would have some tips in what problems

I will probably face using this scenario?

Thanks

Carlos

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

In the purchase order give the account assignment as Q in case u want to receive the material and keep it as project stock. Else give P if u want to consume as you receive the material. Give the WBS element. Note you need to create the WBS element use transaction CJ20N to create the WBS element.

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi

Create a PO with Acct assign category P or Q, so that in the PO line item Account assignment Tab enter the WBS element based on which you need to procure

In the background , for the PO document type, allow one of the item category as P or Q in IMG settings MM>Purchasing >PO>Define Document Types

In the material master record , accounting1 view, you need to enter the project stock valuation class so that the appropriate g/l account will be triggered if that valuation class is assigned to G/l act in OBYC