How to define the operation can be executed on either this work center 'A'or this work center 'A' ?

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

For ur requirement, you have to go for Alternate sequencing.

1)First u create Routing with single work center for all the opeartions. This is called Standard sequence.

2) Go into particular Routing by CA02.

3) Click on "Sequence" tab. You have created already routing, so u can see the Standard sequence with Key ' 0'.

Here create a new sequence of type "Alternate"

4) Then it will ask from which operation, this sequence Starting and Ending. U give here the operation numbers.

For ex: the alternate sequence may start at operation 0020 and end at operation 0050.

5) then u give the operations details for this sequence as usual as u gave in standard sequence.

6) After creation u can see the entire Routing in Graphical mode by clicking on Graphic button. Here u can verify whether u created properly or not.

I think it can clear ur doubt.

Kiran.

Former Member
0 Kudos

I have no of operations in one routing and every operation is having different work centers.

Suppose,

Operation - 10, Work Center - MWS or MWS1 or MWS 2

Operation - 20, Work Center - HMC1 or HMC2

Operation - 30, Work Center - Makino1 or Makino2 or Makino3 or Makino4 or Makino5

Former Member
0 Kudos

Hi ,

In ur case we can create (3x 2 x 5) 30 Alternate sequences. But it is not a practical solution.

Sol 1:

Create Std. sequence with most frequently used W.C s like MWS, HMC1, Makino 1.

Then create parallel sequneces for remaining work centers.

Sol 2:

Create more number of Routings with the different combinations of Work centers and use Production versions concept.

Sol 3:

Create Std. sequence with most frequently used W.C s and ask the End users to change the work centers whenever necessary before Releasing the Order.

Sol 4:

Create machines as number of capacities in a single work center, Then u will have only 1 Work Centers for each operation. Still u will account for cumulative capacity.

I hope Solution 3 will solve ur problem in a practical way.

Experts, welcome for better solution if any.

Kiran.

Edited by: S G Kiran on Oct 13, 2008 9:50 AM

Former Member
0 Kudos

I'll chose the Sol.3 but i thought about this solution before,

To change the work center manually, even we can change the w/c after releasing the order. but SAP should Provide the alternate for operation not for the task list.

Former Member
0 Kudos

I am also looking solution for same. I am a newbie to SAP.

Could you tell me how i can change work center after relasing order.

I should be able to add multiple operation (part order is processed in one work center & other part in different operation) Is it possible?

Pls help

Rupesh

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Create alt routing with alternate workcenter. Use this alt routings in prod version.

Create many production version by tcode C223. In this, for each prod version select alt routings.

By making setting in OPL8, you can manually select the prod version.

Regards,

Dharma