Skip to Content

Archived discussions are read-only. Learn more about SAP Q&A

operation sequence

How to define the operation can be executed on either this work center 'A'or this work center 'A' ?

replied

Hi ,

In ur case we can create (3x 2 x 5) 30 Alternate sequences. But it is not a practical solution.

Sol 1:

Create Std. sequence with most frequently used W.C s like MWS, HMC1, Makino 1.

Then create parallel sequneces for remaining work centers.

Sol 2:

Create more number of Routings with the different combinations of Work centers and use Production versions concept.

Sol 3:

Create Std. sequence with most frequently used W.C s and ask the End users to change the work centers whenever necessary before Releasing the Order.

Sol 4:

Create machines as number of capacities in a single work center, Then u will have only 1 Work Centers for each operation. Still u will account for cumulative capacity.

I hope Solution 3 will solve ur problem in a practical way.

Experts, welcome for better solution if any.

Kiran.

Edited by: S G Kiran on Oct 13, 2008 9:50 AM

0 View this answer in context
Not what you were looking for? View more on this topic or Ask a question