Pre-go live activities..?

Former Member
0 Kudos

Hi all

Can anybody explain me about what are all the pre-go live activities we have do in MM view.

In my client place , 20000 material masters are there , in that 15000 materials with some stock.

How we can create materials master and stock upload for the same .

Thanks

'sap-mm

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Make sure that you are ready with the LSMW and BDC programs for these materials to upload .

Once you upload the materials,make stock postings.

Thanks,

Seshadri

Answers (1)

Answers (1)

former_member192897
Active Contributor
0 Kudos

As per ASAP Methodology and in general also, following sequence is to be followed for Project Go-Live;

Upload of Master Data in Sequence on Test

Start entry of Open Sales Orders, Quotation, Enquiries, Purchase Orders in Prod

Stock Taking Activity at Plant

Stock Upload with SAP Material Code, Qty, Value and Storage Location as on Go-Live Date

Enter Cash Balances as of Go-Live Dates

Enter Excise balances as of Go-Live Dates with monthly duty payment for March

Configure Cut off Excise Number Range (Excise Invoice, RG registers) as on Go-Live Dates

Back up of Loaded Production Server

Go Live