hi

We r using CJ40 and unit costing where v r planning materials.

i want to transfer these planned material to be transferred to projects ( networks). How?

Regards

KP

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

It is not possible to transfer material codes you have used for unit cost planning. Actual material will have to be attached to network activities manually. As of now i.e. in ECC 6.0 there is no facility to transfer the material codes used in unit cost planning to be used for procurement directly. However, there is a facility called easy cost planning. Material code used there can be converted as procurement item using easy execution services.

Former Member
0 Kudos

??

Former Member
0 Kudos

I did not get what you said by "??".