Hi,all,
This is my first implementation project.Our project is now final preparation phase.In my PM module,I have uploaded all relevant master data in production server.Our go-live date is on 15th oct'08.What are the other activities I need to do? Like other module is uploading cut-over data like initial stock,open PO,etc.?In PM module is there any cut-over data concept. and also on 15th or from 15th Oct,08, is it required to manually enter some transactional data for 1st oct'08 to 15th oct'08??Please,suugest me in details what are precautionary measures I need to take or what the activities I need to do???Your valuable input is solicited.Thanks in advance.
rgds
rajib
Dear,
In PM you have to take care of those transaction which are related to external services, like material procurement, service procurement, material sent to outside for repairing. Here billing documnet should be cleared or it should be noted.
Regards,
Kaushal Rai
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
thanks dudes for your valuable input.
rgds
rajib
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi
1.check all PM number ranges are created.
2.Sapres stock uplaod
3.PM activity types assgined to all cost centre in KP26
4.Maintenance plans - you need to be carefull on start up dates in plans.
5.External service POs and orders to be created on GOKLIVE
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Rajib,
All planned maintenance has to be carried out and completed before mm-dd-yyyy as far as practicable. All stores and spares required for these activities be issued for maintenance before mm-dd-yyyy and treated as consumed in Financial Accounting.
No unplanned maintenance activities that cannot be completed before mm-dd-yyyy be commenced after mm-dd-yyyy, except in case of emergencies.
However all stores and spares required for the purpose also be requisitioned and issued in advance by mm-dd-yyyy.
There shall be no Maintenance Orders in SAP for consideration in respect of incomplete maintenance activities as on mm-dd-yyyy. After Go-live maintenance orders will be created for all work getting done.
N.B.: mm-dd-yyy = Go-live date
Rajesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
dear rajib
As you have uploaded master data in production server...now follow all these steps before go-live :
1. prduction system readiness
A. indentify transport requests & approvals
B. all requests transport to production
2. data conversion
perform data conversion to production system
3. cut over
perform cut over to production system
then go -live
regards
vineet
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.