Hi,all,

This is my first implementation project.Our project is now final preparation phase.In my PM module,I have uploaded all relevant master data in production server.Our go-live date is on 15th oct'08.What are the other activities I need to do? Like other module is uploading cut-over data like initial stock,open PO,etc.?In PM module is there any cut-over data concept. and also on 15th or from 15th Oct,08, is it required to manually enter some transactional data for 1st oct'08 to 15th oct'08??Please,suugest me in details what are precautionary measures I need to take or what the activities I need to do???Your valuable input is solicited.Thanks in advance.

rgds

rajib

Accepted Solutions (1)

Accepted Solutions (1)

former_member192718
Active Contributor
0 Kudos

Dear,

In PM you have to take care of those transaction which are related to external services, like material procurement, service procurement, material sent to outside for repairing. Here billing documnet should be cleared or it should be noted.

Regards,

Kaushal Rai

Answers (4)

Answers (4)

Former Member
0 Kudos

thanks dudes for your valuable input.

rgds

rajib

Former Member
0 Kudos

hi

1.check all PM number ranges are created.

2.Sapres stock uplaod

3.PM activity types assgined to all cost centre in KP26

4.Maintenance plans - you need to be carefull on start up dates in plans.

5.External service POs and orders to be created on GOKLIVE

-ashok

Former Member
0 Kudos

Dear Rajib,

All planned maintenance has to be carried out and completed before mm-dd-yyyy as far as practicable. All stores and spares required for these activities be issued for maintenance before mm-dd-yyyy and treated as consumed in Financial Accounting.

No unplanned maintenance activities that cannot be completed before mm-dd-yyyy be commenced after mm-dd-yyyy, except in case of emergencies.

However all stores and spares required for the purpose also be requisitioned and issued in advance by mm-dd-yyyy.

There shall be no Maintenance Orders in SAP for consideration in respect of incomplete maintenance activities as on mm-dd-yyyy. After Go-live maintenance orders will be created for all work getting done.

N.B.: mm-dd-yyy = Go-live date

Rajesh

vineet_sharma4
Participant
0 Kudos

dear rajib

As you have uploaded master data in production server...now follow all these steps before go-live :

1. prduction system readiness

A. indentify transport requests & approvals

B. all requests transport to production

2. data conversion

perform data conversion to production system

3. cut over

perform cut over to production system

then go -live

regards

vineet