IN TXN-MD61 PIR'S to be considered in Month End But Not on Month Beginning

Hi,

When I enter my Finish goods (FERT)requirements In TXN-MD61 and in user Parameters I have selected period indicator as M(Month) and when Saved the requirements date is showing as month beginning where as my requirement is that it should take it as last working day of that month. Here I con not select D (Day) in user Parameters of period indicator. Please Suggestu2026u2026u2026u2026

Hari

Former Member