Pre-go live activities..?

Former Member
0 Kudos

Hi all

Can anybody explain me about what are all the pre-go live activities we have do in MM view.

Like n mumber of master data is there in my client place ..like materials master , vandor master ...etc

How to maintain these materialsand vendor into system before go-live..

Thnaks

sap-mm

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

hi

you have to maintain

1.Material master to be ready to be uploaded.

2. Vendor master. and other master data9if required)

3. Intial stock uploaded.open Po , g/l balances.

4. checking of all the customising request.

5. testing of all scenarios of MM

Regards,

vijay

Answers (1)

Answers (1)

Former Member
0 Kudos

Any body give some inputs

Thnaks

sap-mm

Former Member
0 Kudos

upload open transactiopn like open PO, contract etc.

condition records

info records, source list update

user settings

user authorization is biggest issue like user have no authorization to change the PO or can create anything etc.

W.r.t. Go-live, Inital stock balances upload is vital activity. The errors in this activity influences the trial balance.

Awareness to key users for collecting data.

This activity must be ensured for all the stocks at all the locations. Care must be ensured to map the new org structures (storage loc, warehouse, sotrage type etc).

Also refer

http://www.sapfans.com/sapfans/asap/be_07_e.htm

Thanks,

seshadri