Dear all,

I have one scenario where I hv to update Breakdown Statistics for a plant.

There are some utility machines say DG SET ot the Main Transformer breaker if these machine goes under breakdown the whole plant goes under breakdown i.e. i cant use the plant machines for production because power is not availble.

For Plant Maintenance it is the breakdown of the Utility Equipment and not of the Production Machine.

Please advice me how I can adress this Breakdown time for dependent Equipments?

Also When Production Person will confirm the Production Order how he can book the Breakdown time.